Neil Leitz
Senior Capstone Project
Central Washington University
Budget
The budget for this project is detailed in the graphic at the right. The total budget for the project was $629.45, which did not exceed the required price cap of $750.
The majority of the budget was spent on torsion axle stubs, as they were viewed as neccesary to help absorb some bouncing motion of the trailer as neccesary.
The trailer was primarily constructed from 3" x 2" x .120" ASTM Grade B steel tubing.
Schedule
The full schedule for this project can be viewed in Gantt chart form here. The project had three phases, namely the planning/analysis, production/construction, and testing phases. The phases were further divided into tasks with specific task ID's. The completion window for each of this tasks was clearly marked and labeled on the Gantt chart.